Installation Procedure - Curb System
For substation or storage tank containment areas of 20 ft x 30 ft or smaller water flow rate of up to 20 gal/hr before imbiber beads® are activated.GAL STEEL HOUSING | Stock # IMSHC121218-SS

GAL STEEL HOUSING 11 1/4 "W X 16 1/4 "X 12"HEIGHT WITH A 6" X 6" DROP AT ONE END
Components per unit:
• IMSHC121218-S - GAL STEEL HOUSING - REMOVABLE TOP (1)
• IMOD0603-3 - IMBIBER BEADS® SHUT OFF DISC (1)
• IMBCR505016-R - IMBIBER BEADS® /SAND CUSHION (1) IM1421-EA
• IMBIBER BEADS® PILLOW (1)

Unit is fitted to locate drill
holes and plugs in cement
( or tapcon concrete screws
3/16" x 1 1/4")
(for later anchoring unit)
holes and plugs in cement
( or tapcon concrete screws
3/16" x 1 1/4")
(for later anchoring unit)

Watertight / solvent
resistant caulking is
applied around opening
resistant caulking is
applied around opening

Unit is fitted in place

After unit is fitted in place
bolts are inserted through
flange holes anchoring unit
bolts are inserted through
flange holes anchoring unit

Final step after unit is anchored: watertight / solvent resistant caulking is applied around its base & flange edges
FOR SUBSTATION OR STORAGE TANK CONTAINMENT AREAS OF 20 FT X 30 FT OR SMALLER WATER FLOW RATE OF UP TO 20 GAL/HR BEFORE IMBIBER BEADS® ARE ACTIVATED.
CUSTOMER RESPONSIBILITY: WALL PLUGS - BOLTS - WATERTIGHT / SOLVENT RESISTANT CAULKING